Conflicts detected!
A red frame around the affected process now immediately shows where there are conflicts. This allows you to directly identify and resolve potential problems when changes are made to the planning.
If a conflict process is selected, the "Conflict detected" info button appears at the top center, which can be used to open another conflict menu.
Resolve conflicts
The focus button is used to focus on all processes within the linked process chain. Processes that are in the direct connection are outlined in red and highlighted in yellow in the process details.
By clicking the button, the lead time of the existing dependency is adjusted. For example, if there is a process overlap of one day, the dependency is changed from EA+0d to EA-1d. The conflict is therefore not resolved by shifting, but by adjusting the link.
Select "Resolve conflict" to automatically postpone all affected processes according to when the dependency is exceeded. The numbers in the red circles indicate by how many days the process will be postponed into the future.
The conflict menu only closes once the "X" button has been pressed, even if the conflict has been resolved.