Import/Export |
-
When uploading files, you now have the option of uploading P6 files.
- When you upload the P6 file, you still need to select a column from your P6 file to be displayed in the process plan as trades.
-
Plase note, that this function is been released in beta-version. We are happy about your feedback via support@lcmd.io.
- As a user, you can now decide for yourself whether the exported processes should arrive in Microsoft Project manually or auto scheduled.

-
- There is also the option to ignore processes that were added after the baseline was set and not to export them.
- The sorting of the processes now corresponds to the same sorting as in lcmd.
- The columns “Number 19” and “Number 20” are used in Microsoft Project to display the target value and the difference between the target and actual values.
- Holidays are exported to keep the same overview.
- The sum bars are calculated.
|