*** HIGHLIGHT *** Import | |
| Process Plan | |
| Project options | - Users with restricted area access cannot duplicate the corresponding project.
- Trade filters from the user role are not transferred to the admin when duplicating a project. The admin role cannot have any trade restrictions.
|
| Export | - The process owner is exported to Excel in a separate column.
- If the "additional ID" is used for the process from P6 Import, it is now also exported to Excel.
- Only areas for which the user has visibility permissions are exported to MS Project.
|
| Usability | - A message appears when an incorrect format is uploaded for area images. See here which formats can be imported.
- The message when searching in the project list has been adjusted.
- Display a message when resetting filters.
- A message appears when changing profile settings (top right "man" icon).
- Newly registered users can use an automatically provided sample project.
- Text in comments can be copied.
- Long process names are displayed in full in the black tooltip for the process.
- When selecting multiple processes, the information display with conflicts is not displayed.
- Optimizations for displaying long trade names in the filter.
|