Problem
The import of the process plan from Excel fails and you receive an email with an error message about the process duration.
Solution
In order to import a process plan from Excel correctly, the start date and the duration in working days are necessary. The end date is then calculated from this.
If you add the column "Duration" or do not leave it empty and enter the respective duration in working days, you can import the data.
If you have this problem or further questions about the correct import format, you can find more details here.
We are also happy to support you with this support@lcmdigital.com