What's new in LCM-1.2.2?
the focus of the current release is the platform stabilization and performance improvements.
New functions for data interfaces have been added, such as file attachments for fragnet steps or the possibility to import process plans from Excel files. In addition to numerous bug fixes, the PDF export has been optimized.
Known issues, which are still being worked on, will be added in upcoming patches.

New Features
Attachments
Attachments can be added to fragnet steps and managed in the Panel. Details here (Attachments).
Export and import of process plans in Excel
Process plans are exported in Excel format (previously CSV). Newly added is the possibility to import process plans from Excel files. Details here (Import from Excel - PP).
Export PDF in progress mode
The progress mode of a process plan can be exported to PDF. Details here (Process Plan - Section Export the Process Plan to PDF).
Takt Zones inherit images / colors automatically
When automatically generating takt zones, you can select whether the images and colors of the respective zone type should be inherited. Details here (Takt zones - Automatically generate takt zones).
Change requests from users
| Action Items, Stability Criteria & Comments |
|
| Cloning |
- Bug fix when cloning projects
|
| Daily Board/ Job Cards |
- Optimized export of job cards
|
| Data Integrity |
- Bug fix when removing items in the project data, e.g. areas
- Bug fix when assigning trades to companies
- Bug fix when adding material to a fragnet step
|
| Fragnet Grid Behavior |
- Optimized display of non-working days in the process plan
- Bug fix when dragging fragnet steps into the grid
- Partial bug fix when moving several fragnet steps at once in the process plan
|
| PDF Export |
- Use the whole height of the process step for names
- Bug fix when generating PDF files
- Partial optimization of the header for logos (height, scaling)
- PDF export on one page
- Manpower chart respects values of filtered trades
- Bug fix of additional exported days at the start/end of an exported time frame to PDF including milestones and links
- Optimized diplay of fragnet steps in daily view
- Optimized size of the timeline (year, month, calendar weeks) in weekly view
|
| PP Generation / Regeneration |
- Bug fix of same name assignment / set to official process plan when regenerating the process plan
- Partial bug fix when regenerating the process plan after changes in the calendar
|
| Security |
- Complete project view for account manager in his account
- Partial bug fix when locking takt zones by users
|
| Usability |
|
| Visuals |
- Optimized zoom behavior of the calendar weeks in the timeline
|
Further improvements / bug fixes
| Daily Board / Job Cards |
- Exporting job cards respects the current filtering of takt zones and trades
|
| PDF Export |
- The colors of zone types / takt types / takt zones are displayed in the PDF export
|
| Milestones |
- Optimized display of milestones (Focus and graying out when selected)
|
| Action Items, Stability Criteria & Comments |
- Bug fix when showing error message in empty action list
|
| Data Integrity |
- Optimized naming od automatically generated takt zones (takt type name is included)
|
| Fragnet Grid Behavior |
- Bug fix of overlapping fragnet steps in expanded takt zones in the takt zone iteration
|
| Milestones |
- Optimized sorting od the date columns of the milestone panel
- Optimized zoom in expanded milestone section
- In the edit form of a milestones CTRL+A can be used to select the whole content of a field
|
| PDF Export |
- Optimized header of the process plan
- Bug fix of misplaced link arrows in PDF export (fixed for the takt analysis, process planning will follow soon)
- Optimized wrapping of long milestone names in PDF export
- Optimized display of milestones in the PDF export
|
| PP Generation / Regeneration |
- Bug fix for the order of fragnet steps after regenerating the process plan because of changed non-working days in the calendar
- Bug fix for unwanted spaces between fragnet steps after regenerating the process plan
|
Known issues
| Attachments |
- Partially incorrect display of attachments on the icon after regenerating the PP
|
| Forms |
- Inactive fields when editing several fragnet steps at one in the PP
- Optimized focus of calendar/color forms
|
| Import/Export |
- Further optimization of fragnet step durations when reimporting process plans (only projects with different calendars)
|
| Fragnet Grid Behavior |
- Further optimization for moving several fragnet steps at once in the process plan
|
| Links |
- Display of multiple links after regenerationg the process plan
|
| Milestones |
- Missing values in the "Description" column when exportimg milestones
|
| PDF Export |
- Further optimization of the header - skip white spaces
- Bug fix for misplaced link arrows in the PDF export of the process plan (already fixed for the takt analysis)
- Optimization of label font sizes for the TA PDF export
- Display error of filtered fragnet steps with a one-day duration in the takt analysis
- Further optimization when exporting empty takt zones
- Legend for the PDF export in progress mode
|
| PP Generation / Regeneration |
- Further bug fixes when regenerating the process plan after changes in the calendar
|
| Usability |
- Translations of several error messages in the overall process analysis and the project data for the german language setting
- Further opimization of the performance
|
| Security |
- The page must be reloaded after clicking on the lock icon to unlock takt zones
- Red background error messages
|
| Mobile App |
- Optimized synchronization of attachments between platform and app
|